A bathroom renovation in Toronto in 2026 costs anywhere from $12,000 for a budget refresh to $60,000+ for a full custom build. The range is wide because bathroom costs are driven by three variables: how much plumbing you move, how much tile you install, and what finish level you choose.
At a glance: bathroom renovation costs in Toronto (2026)
| Bathroom type |
Cost range |
Typical timeline |
| Powder room (2-piece) |
$6,000-$12,000 |
1-2 weeks |
| 3-piece bathroom |
$14,000-$25,000 |
2-3 weeks |
| 4-piece / main bathroom |
$20,000-$35,000 |
3-4 weeks |
| Primary ensuite |
$30,000-$60,000+ |
4-8 weeks |
| Condo bathroom |
$15,000-$30,000 |
3-5 weeks |
| Budget refresh (vanity, toilet, paint) |
$12,000-$18,000 |
1-2 weeks |
| Mid-range renovation |
$20,000-$35,000 |
3-4 weeks |
| Full custom renovation |
$35,000-$60,000+ |
4-8 weeks |
Sources: HomeStars 2026 Toronto Bathroom Renovation Cost Guide, City of Toronto Building Permit Fee Schedule, Adept Renovation project records.
Line-item breakdown: where the money goes
For a typical 4-piece main bathroom (mid-range finish, no layout changes):
| Line item |
Cost range |
% of total |
| Demolition and disposal |
$800-$1,500 |
3% |
| Plumbing (rough-in, fixtures, valves) |
$3,000-$6,000 |
14% |
| Electrical (rewiring, lighting, exhaust fan, GFCI) |
$1,500-$3,500 |
8% |
| Waterproofing membrane and labour |
$1,500-$3,000 |
7% |
| Tiling (walls + floor, mid-range tile) |
$3,500-$7,000 |
17% |
| Vanity + countertop |
$1,500-$4,000 |
9% |
| Toilet |
$400-$1,200 |
3% |
| Shower system / tub |
$1,500-$4,000 |
9% |
| Glass shower enclosure |
$1,200-$3,000 |
7% |
| Paint, trim, mirrors, accessories |
$800-$2,000 |
4% |
| Labour (general contractor coordination) |
$5,000-$10,000 |
19% |
| Total (mid-range 4-piece) |
$20,700-$45,200 |
100% |
Labour accounts for 40% to 60% of most bathroom renovation quotes in Toronto, making contractor selection one of the most important budget decisions. For help choosing, see our bathroom renovation companies guide.
Cost by scope type
Powder room (2-piece: toilet + sink)
| Line item |
Cost range |
| Vanity + toilet + mirror |
$1,500-$3,000 |
| Floor tile (small space, 20-40 sq ft) |
$800-$2,000 |
| Paint, trim, accessories |
$500-$1,500 |
| Plumbing (if relocating) |
$1,000-$3,000 |
| Total (no plumbing move) |
$6,000-$10,000 |
| Total (with plumbing move) |
$8,000-$12,000 |
Powder rooms are the lowest-cost bathroom renovation because there's no shower or tub: no waterproofing, no glass, minimal tile.
3-piece bathroom (toilet, sink, shower)
| Scope |
Cost range |
| Standard scope (keep layout) |
$14,000-$20,000 |
| With new tile throughout |
$16,000-$25,000 |
| With plumbing relocation |
$20,000-$30,000 |
The jump from 3-piece to 4-piece is usually $5,000-$10,000, driven by the bathtub or tub-to-shoulder tile transition.
4-piece / main bathroom (toilet, sink, tub, shower)
| Scope |
Cost range |
| Standard scope (keep layout) |
$20,000-$28,000 |
| With upgraded tile + fixtures |
$25,000-$35,000 |
| Full gut + layout change |
$30,000-$45,000 |
The biggest cost driver in a 4-piece bathroom is tile quantity and quality. A full tub-to-ceiling tile surround costs 2 to 3 times more than a half-wall tile backsplash.
Primary ensuite
| Scope |
Cost range |
| Standard upgrades (same layout) |
$30,000-$40,000 |
| Custom shower + double vanity + heated floors |
$40,000-$60,000+ |
| With layout change + structural work |
$50,000-$80,000+ |
Ensuites cost more because they're larger, use more tile, and typically include custom showers with glass enclosures, double vanities, and heated flooring. In dozens of GTA bathroom projects over 12 years, the primary ensuite is the renovation homeowners cite most often when preparing a home for resale. It is also the highest-ROI bathroom investment on a per-square-foot basis (CMHC, 2024).
Condo bathroom
| Scope |
Cost range |
| Standard update (no layout change) |
$15,000-$22,000 |
| With board approvals + elevator booking |
$18,000-$30,000 |
| With plumbing relocation |
$22,000-$35,000 |
Condo bathrooms carry a premium because of building logistics: board approval applications, insurance certificates, elevator bookings, strict work hours, and common-element protection requirements add $2,000-$5,000 in soft costs that don't exist in a house. Budget an extra $2,000-$5,000 for soft costs if your project is in a downtown Toronto condo.
Cost by GTA neighbourhood
Pricing shifts across the GTA based on contractor demand, condo rules, and site access:
| Area |
Price adjustment |
Why |
| Downtown Toronto condos |
+10-20% |
Elevator bookings, board approval fees, insurance certificates, restricted work hours |
| Midtown / Yonge and Eglinton |
+5-10% |
Condo-heavy area with similar building logistics, high contractor demand |
| Etobicoke and west end |
Baseline |
Good contractor availability, mostly houses with easy site access |
| North York |
Baseline |
Mix of houses and condos, competitive contractor market |
| Scarborough |
-5% vs baseline |
Less dense, easier access, lower site logistic costs |
| Mississauga |
Baseline |
Similar to Toronto rates with easier parking and access |
| Oakville / Burlington |
+5-10% |
Higher-end finishes more common, pushing average project cost up |
| Brampton / Vaughan |
Baseline to -5% |
Competitive market with good contractor availability |
What drives your bathroom cost up or down
| Factor |
Cost impact |
Why |
| Moving plumbing |
+$5K-$15K |
Relocating a toilet or shower drain means cutting the slab and new drain lines |
| Tile quality |
+/-$3K-$10K |
Porcelain = affordable; natural stone, large-format, or herringbone pattern = premium |
| Shower system |
+/-$2K-$8K |
Basic thermostatic valve vs. digital multi-function system with body sprays |
| Glass enclosure |
+/-$1K-$5K |
Frameless glass with custom hinges costs 2x framed |
| Condo board requirements |
+$2K-$5K |
Applications, certificates, elevator protection, insurance requirements |
| Heated floors |
+$2K-$4K |
Electric radiant in-floor heating, material + labour |
| Layout change |
+$5K-$20K |
Moving walls changes everything: structural, plumbing, electrical |
Bathroom renovation timeline: what to expect
| Scope |
Planning & design |
Material lead time |
Permits |
Construction |
Total |
| Budget refresh (paint, vanity, toilet) |
1 week |
1-2 weeks |
Not required |
1-2 weeks |
2-4 weeks |
| Mid-range renovation (keep layout) |
1-2 weeks |
2-3 weeks |
2-3 weeks (if plumbing moves) |
2-4 weeks |
6-9 weeks |
| Full custom (layout change, premium) |
2-3 weeks |
3-6 weeks |
3-6 weeks |
4-8 weeks |
10-16 weeks |
| Condo bathroom |
1-2 weeks |
2-4 weeks |
2-4 weeks (board + permits) |
3-5 weeks |
8-13 weeks |
Planning and design includes on-site measure, scope discussion, material selection, and finalized drawings. Material lead time depends on what's in stock: off-the-shelf tile ships in days, but custom vanities or imported stone take 4-6 weeks.
Construction sequence: week by week
| Stage |
Duration |
What happens |
Common delay |
| Demolition |
1-3 days |
Remove old fixtures, tile, flooring; open walls if needed |
Hidden water damage, mold, or outdated plumbing found behind walls - the most common delay discovered during demo |
| Rough-in (plumbing, electrical, framing) |
2-5 days |
Relocate plumbing lines, rewire lighting, frame new walls |
Moving a toilet drain or shower pan requires cutting the slab, adding 2-3 days |
| Waterproofing and drywall |
3-5 days |
Cement board, waterproof membrane, drywall hang and tape |
Second coat of waterproofing sometimes required in high-moisture condos |
| Tile installation |
4-7 days |
Wall and floor tile, the longest single construction stage |
Large-format tile, herringbone patterns, or natural stone all install slower than standard subway tile |
| Fixtures and finishing |
3-5 days |
Vanity, toilet, shower system, glass enclosure, mirrors, paint |
Custom glass enclosure can't be installed until walls are fully tiled, so any delay upstream pushes this out |
| Final walkthrough and punch list |
1-2 days |
Touch-up paint, caulking, cleaning, inspection |
City inspection scheduling delays - book inspections early |
Three biggest causes of delays
Material not on site when demo starts. The #1 schedule killer. Contractors can't install what hasn't arrived. Order everything - tile, vanity, fixtures, shower glass - before demolition begins, and confirm all lead times in writing.
Mid-project scope changes. "Actually, let's move the shower to that wall" mid-rough-in means replumbing, re-framing, and sometimes re-permitting. Finalize every decision during the design phase - changes after demo cost time and money.
Permit and condo board delays. A City of Toronto permit review takes 2-6 weeks for bathroom renovations that move plumbing. Condo board applications add another 2-4 weeks, plus elevator booking fees and restricted work hours that can halve your daily work window.
How much time each cost driver adds
| Factor |
Time added |
Why |
| Moving plumbing (toilet or shower) |
+3-7 days |
Cutting slab, new drain lines, extra inspections |
| Custom vanity (built, not stock) |
+2-4 weeks lead time |
Fabrication queue, order 6 weeks ahead |
| Large-format or natural stone tile |
+2-4 days install |
Heavier, slower to cut, more prep |
| Heated floors |
+1-2 days |
Electric radiant mat installation under tile |
| Condo board approval |
+2-4 weeks |
Application review, insurance certs, elevator booking |
| Hidden water damage |
+3-7 days |
Remediation, drying time, re-sheathing |
How to keep your bathroom renovation on schedule
- Order everything before you sign the contract. Tile, vanity, toilet, tub, shower system, glass enclosure, lighting - if it's not on site or confirmed for a delivery date, don't start demo.
- Don't change your mind mid-project. Every "while we're at it" request adds days and dollars. Stick to the plan.
- Get permits submitted early. Your contractor should apply the day you sign, not wait until demo starts.
- Condo owners: start the board process 4-6 weeks before your planned start date. Elevator bookings fill up, insurance certificates take time, and restricted hours (often no work before 9 AM or after 5 PM) mean fewer productive hours per day.
- Add a 1-week buffer. Even well-planned projects hit surprises. Budget a week of float in your schedule - it's the difference between stress and peace of mind.
Frequently asked questions
Can I use my bathroom during the renovation?
Almost never. The toilet, sink, and shower are disconnected during demolition and remain out of service until fixtures are reinstalled late in the process. Plan for an alternate bathroom (or a rented porta-potty) for the construction period.
Does a small bathroom take less time?
Not necessarily. A small space often demands more precise tile cuts, tight-access plumbing work, and careful layout - the timeline is usually the same as a mid-size main bathroom.
How much longer does a condo bathroom take?
Expect 2-4 weeks more than a house bathroom due to board approval, elevator booking, restricted work hours, and common-element protection requirements.
What's the fastest way to finish?
Keep the layout the same, use stocked materials (no custom orders), and have everything on site before demo. A straightforward like-for-like refresh can be done in 1-2 weeks of construction.
Do you need a permit for a bathroom renovation in Toronto?
| Scope |
Permit required? |
| Like-for-like replacement (same toilet, same vanity location) |
No |
| Moving plumbing or relocating fixtures |
Yes |
| Changing electrical or adding new circuits |
Yes |
| Removing or adding walls |
Yes |
| Condo bathroom with any changes to common elements |
Yes |
Permit fees for a bathroom renovation in Toronto run approximately $150-$400 under the City's 2026 fee schedule ($11.53 per m2 of interior alterations). Designer drawings add $1,000-$3,000. A reputable contractor handles all permit submissions and inspections on your behalf.
How Adept Renovation handles bathroom projects
We've completed dozens of bathroom renovations across the GTA, from small condo powder rooms to full primary ensuite gut renovations. Our process:
- Free on-site estimate: we measure, discuss your scope, and give you a fixed-price line-item quote
- Permits handled end-to-end: we manage drawings, submissions, condo board applications, and inspections
- In-house drywall, tiling, and painting crews: no subcontractor coordination gaps between trades
- Fixed-price contract: the price we quote is the price you pay
- 5-year workmanship warranty on all work
For help choosing a contractor, see our Best Bathroom Renovation Companies in the GTA guide and How to Hire a Renovation Contractor in Toronto.
About the author: Awat Hamid is the owner of Adept Renovation & Painting, a Toronto-based renovation contractor specializing in bathroom renovations, kitchen renovations, drywall, and interior painting.
Sources
Ready to start your bathroom renovation in Toronto?
Adept Renovation & Painting has been transforming Toronto bathroom renovations, from powder room refreshes in downtown condos to full primary ensuites in North York, Scarborough, Etobicoke, and Mississauga, since 2014. We're fully licensed and insured in Ontario, and we handle everything from design consultation and permits to skilled trades and project management.
Get a free, no-obligation bathroom renovation quote. We'll walk through your space, discuss your budget and timeline, and give you a detailed line-item estimate. No pressure, just honest numbers.
Serving Toronto, Oakville, Brampton, Etobicoke, Mississauga, and the entire GTA